Measure the deck surface
Multiply length by width for the area. Measure the open sides separately for railing, and count the steps down to the yard.
Home › Deck
Deck costEstimate the cost to build or replace a deck: square footage and board material, height, railing, stairs, demolition and permits, with a check on what insurance would pay after a covered loss.
Reviewed November 20, 2026 · Written by Mantu Kumar
Sources: RemodelAI and NerdWallet, listed at the end of this page.
2026 planning ranges
300 sq ft, installed: Pressure-treated $4,500–$7,500 Composite $9,000–$18,000 Permit $50–$500
Diagram, part by part
The deck drawing above has 9 numbered parts, from Ledger bolted and flashed to Old deck tear-out. The cards cover joists and beam, decking and the other deck parts. Once you calculate, included items carry their own amounts.
Part of the frame price
The ledger is the board bolted to the house that carries one side of the deck. It needs through-bolts or structural screws into the rim joist and flashing over the top so water cannot rot the house framing. A poorly attached ledger is the most common cause of deck collapses.
What moves it: Deck width along the house and the house siding type.
On the quote: Ask how the ledger is fastened and flashed, and whether siding is removed behind it.
in the frame rate
Joists and beams form the frame. Their size and spacing depend on the span, the decking material and the load, and composite decking often needs closer joist spacing than wood.
What moves it: Deck size, height and decking material.
On the quote: Ask for joist size and spacing, and whether hangers and hardware are hot-dip galvanized or stainless.
PT $15–$25, composite $30–$60/sq ft
The walking surface. Pressure-treated wood is cheapest; cedar and redwood look warmer; composite and PVC cost more but need less upkeep; tropical hardwood is the most durable and the most expensive.
What moves it: Area and the decking material.
On the quote: Ask for the decking brand and grade, and the fastening method, hidden clips or face screws.
Part of the frame price
Posts sit on concrete footings below the frost line so the deck does not heave or settle. Footing size and depth come from the deck load and local code.
What moves it: Number of posts, footing depth and soil.
On the quote: Ask for footing diameter and depth, and whether posts sit on brackets above the concrete.
$20–$80 per ft
Railing is priced per linear foot and is required when the deck is more than about 30 inches above the ground. Wood is cheapest; composite, aluminum, cable and glass cost more.
What moves it: Railing length and material.
On the quote: Ask for railing height and baluster spacing so a 4-inch sphere cannot pass through.
$50–$150 per step
Stairs are priced per step and include stringers, treads and handrails, often with a concrete landing pad at the bottom.
What moves it: Number of steps and the railing type.
On the quote: Ask whether stair railings and the landing pad are included.
$100–$500
Most decks attached to a house or more than about 30 inches high need a permit, with inspections of the footing holes, the framing and the finished deck. Skipping it can cause problems when the house is sold.
What moves it: Deck height, size and your town's fee schedule.
On the quote: Ask who pulls the permit and which inspections are scheduled.
Second-story decks cost more to frame
A low deck under 2 feet needs short posts and often no railing. A second-story deck needs longer posts, bracing and safety rigging during construction, which raises the framing cost.
What moves it: How high the deck sits above the ground.
On the quote: Ask whether bracing and taller posts are included for a high deck.
$1,500–$4,500
Removing an old deck means unscrewing or cutting the boards, pulling the frame and hauling the debris. Old pressure-treated wood cannot be burned and must be disposed of properly.
What moves it: Deck size, height and whether footings are pulled.
On the quote: Ask whether old footings are removed or reused and who hauls the debris.
On the deck itself
The photograph is taken from the deck, so the surface, the wall it meets and the stairs down to the yard are all visible.

Look closer at three details before you compare deck quotes. Use them with the checks underneath.

Multiply length by width for the area. Measure the open sides separately for railing, and count the steps down to the yard.

An attached deck hangs on a ledger fastened to the house. Ask how it is bolted and flashed. That joint is the detail that fails first if water gets behind the siding.

Height above grade sets post size, bracing, railing and how many steps you need. A slope often means taller posts at one end.
| Decking | Installed per sq ft | Typical life |
|---|---|---|
| Pressure-treated pine | $15 – $25 | 10 to 20 years |
| Cedar | $25 – $35 | 15 to 20 years |
| Redwood | $30 – $45 | 15 to 25 years |
| Composite | $30 – $60 | 25 to 30 years or more |
| PVC | $35 – $60 | 30 years or more |
| Ipe hardwood | $35 – $60 | 40 years or more |
The framing under almost every deck is pressure-treated lumber, so the board material changes the surface cost, the upkeep and the life more than the structure. Composite and PVC cost more at the start and need no staining.
Railing is required on most decks more than 30 inches above the ground and runs from about $20 per foot in wood to $80 or more in aluminum, and more again for cable or glass. Stairs cost roughly $50 to $150 per step. A second-story deck needs taller posts, bracing and staging, so it costs noticeably more per square foot than one close to the ground.
If the framing is sound, new boards and railing on the old structure can save a third or more. Probe joists, posts and the ledger with a screwdriver; soft wood, rusted fasteners or a missing ledger flashing mean the frame should be rebuilt before new decking goes on. The repair or replace calculator explains the general rules of thumb.
Attached decks are part of the dwelling; free-standing ones are other structures. Storm, fire and tree damage are usually covered, rot and wear are not. If someone is injured on a failing deck, the liability part of the policy responds, which is a strong reason to fix a loose railing promptly.
These are the default inputs on this page, multiplied by the published rates. Region index is 1.00, so only the permit line is flat. A 12 × 25 deck is the same 300 sq ft.
| Decking, framing and footings, $15 – $25 / sq ft | $4,500 – $7,500 |
| Wood rail, 40 linear ft at $20 – $40 | $800 – $1,600 |
| Four stair risers at $50 – $150 | $200 – $600 |
| Permit, not multiplied by region | $100 – $500 |
| Default planning range | $5,600 – $10,200 |
Composite boards use $30 – $60 per sq ft for the decking line only, so the same 300 sq ft decking line becomes $9,000 – $18,000 before rail, stairs and permit. A second-story deck multiplies the decking line by 1.3. Frost depth changes the footing, not a city price list. Age 15 against a 15-year life hits the 80% depreciation cap in the insurance block.
The calculator's default deck job, compared across the six regional settings. At the national average the total is $5,600 – $10,200; South / Lower Midwest is the lowest at $4,885 – $8,939, and West Coast metro is the highest at $7,250 – $13,110, a gap of about $3,268 at the midpoint.
| Region | Planning range | Midpoint |
|---|---|---|
| National average | $5,600 – $10,200 | $7,900 |
| South / Lower Midwest | $4,885 – $8,939 | $6,912 |
| Mountain / Plains | $5,325 – $9,715 | $7,520 |
| Mid-Atlantic / Upper Midwest | $6,260 – $11,364 | $8,812 |
| Northeast metro | $7,030 – $12,722 | $9,876 |
| West Coast metro | $7,250 – $13,110 | $10,180 |
For this deck comparison, keep the default inputs except “Decking”. The cheapest choice, Pressure-treated pine, comes to $5,600 – $10,200; the most expensive, Ipe hardwood, comes to $11,600 – $20,700.
| Choice | Planning range | Midpoint vs default |
|---|---|---|
| Pressure-treated pine (default) | $5,600 – $10,200 | — |
| Cedar | $8,600 – $13,200 | +$3,000 |
| Redwood | $10,100 – $16,200 | +$5,250 |
| Composite (Trex, TimberTech and similar) | $10,100 – $20,700 | +$7,500 |
| PVC | $11,600 – $20,700 | +$8,250 |
| Ipe hardwood | $11,600 – $20,700 | +$8,250 |
For this deck comparison, keep the default inputs except “Railing”. The cheapest choice, No railing, comes to $4,800 – $8,600; the most expensive, Cable or glass, comes to $7,200 – $14,600.
| Choice | Planning range | Midpoint vs default |
|---|---|---|
| No railing | $4,800 – $8,600 | −$1,200 |
| Wood (default) | $5,600 – $10,200 | — |
| Composite or vinyl | $6,200 – $11,400 | +$900 |
| Aluminum | $6,600 – $11,800 | +$1,300 |
| Cable or glass | $7,200 – $14,600 | +$3,000 |
The $1,500 deductible and 15-year expected life apply to the default deck job here. At 10 years old, the item in the deck example has about $5,267 withheld for depreciation. Actual cash value leaves that amount deducted. Replacement cost coverage may release it after completion.
| Age | Wear | First check | Held back |
|---|---|---|---|
| 2 years | 13% | $5,347 | $1,053 |
| 5 years | 33% | $3,767 | $2,633 |
| 10 years | 67% | $1,133 | $5,267 |
| 15 years | 80% | $80 | $6,320 |
| 20 years | 80% | $80 | $6,320 |
| 30 years | 80% | $80 | $6,320 |
Deck quotes are easiest to compare with the same size, decking and railing.
| Stage | Typical time | What happens |
|---|---|---|
| Design and permit | 1 – 6 weeks | Drawings and permit review. |
| Footings | 1 – 2 days | Holes dug and inspected before concrete. |
| Framing | 2 – 4 days | Ledger, beams and joists; framing inspection. |
| Decking, railing and stairs | 2 – 5 days | Depends on material and size. |
| Final inspection | 1 – 14 days | Before regular use. |
Composite decking needs the right joist spacing from day one, so pick the decking before the framing is built.
Deck costs follow size, height and materials.
Safety comes first with decks.
Installed decks commonly run about $15 to $25 per sq ft in pressure-treated pine and $30 to $60 in composite or PVC, before railing and stairs. All-in, professionally built decks often land between $30 and $60 per sq ft.
In pressure-treated pine, 2 to 8 ft high, with 40 ft of wood railing and four steps, this calculator returns about $5,600 to $10,200 at the national average, including a permit allowance.
Composite costs more to build but needs no staining or sealing and typically lasts 25 to 30 years or more, against 10 to 20 for pressure-treated wood. Over the life of the deck the gap narrows.
Usually, for decks attached to the house or more than about 30 inches above the ground. The permit brings plan review and inspections of footings, framing and the ledger.
Yes, if the joists, beams, posts and ledger are sound. Resurfacing with new boards and railing often costs a third less than a full rebuild.
Attached decks are covered as part of the dwelling and detached ones as other structures, for covered causes such as fire, wind and falling trees. Rot, insects and wear are excluded.
Pressure-treated wood decks often last 10 to 20 years, cedar and redwood 15 to 25, and composite or PVC 25 years or more with the framing kept dry.
Pressure-treated pine is common and affordable. Cedar and redwood resist decay naturally and look warmer. Tropical hardwoods such as ipe are very dense and durable but cost more and are harder to work.
Joists are often spaced 16 inches on center. Some composite boards, diagonal patterns and stair treads call for 12-inch spacing; the decking maker sets the limit.
Yes. Flashing over and behind the ledger board keeps water out of the house rim joist. Missing ledger flashing is a common cause of rot that weakens the deck connection.
Many wood decks need cleaning and a new coat of sealer or stain every one to three years, depending on sun, rain and the product used.
The board bolted to the house that supports one side of an attached deck. Its fastening and flashing are the most important safety details on a deck.
Low freestanding decks on deck blocks exist, but many codes require proper footings for attached decks and for decks above a certain height.
Some boards can be slick when wet or icy. Boards with deep embossed texture and keeping the surface clean of algae improve grip.
Per-square-foot prices come from published deck cost guides; structural terms from the American Wood Council deck guide.
These organizations do not endorse ReplaceCost. The written policy, program rules, contractor scope and applicable law control the real result. See the full methodology for the source hierarchy and update process.
Board material sets the surface cost; height, railing and stairs set the rest.
Each tool itemizes the work, shows a planning range, and explains how age, depreciation and your deductible can change the insurance check.
Planning summary: Start with the physical replacement estimator, then run the Claim gap tool with the replacement figure, item age, expected life and deductible from your declarations page. The result is a planning estimate — not a contractor quote or coverage decision.