Trade-unit check
The result must use the unit normally discussed for that project instead of applying one house-wide square-foot rate to every trade.
Home › Methodology
Start with the unit a contractor actually writes on a bid: roofing squares, tons, openings, linear feet, wall or floor area, or installed watts. A house-wide price per square foot is the wrong unit for almost every trade here.
Split material from labor, and both of those from tear-off, disposal, permits and the repairs that show up once the old work is open. If a quote buries those, the total is not comparable.
Change only the lines the condition actually touches. A second story changes access. Pitch changes roof area. Region is a broad labor adjustment, not a ZIP-code promise.
The low end is a straightforward job. The center is for comparing written bids. The high end is difficult access, premium material or related repair. None of the three is a quote.
The low end represents a straightforward job with ordinary access and limited related repair. The midpoint is the center of the modeled range and is useful for comparing written bids. The high end allows for premium selections, difficult access, removal, code work or related repairs selected in the form. None of the three is a contractor quote, appraisal or promised insurance settlement.
Ranges are intentionally wider when the scope is difficult to know before inspection. A hidden roof deck, corroded plumbing connection, damaged window opening or wet subfloor cannot be priced reliably from an online form.
The result must use the unit normally discussed for that project instead of applying one house-wide square-foot rate to every trade.
Material and installation are separated from removal, permits and possible repair so visitors can compare like for like.
Modeled outputs are compared with current public or published reference ranges, while differences in scope are called out.
| Calculator | Base measurement | Major modeled drivers | Primary evidence families |
|---|---|---|---|
| Roof | Roof squares | Footprint, pitch, waste, material, layers, access | BLS labor/PPI, NAIC insurance definitions |
| Solar | Installed watts | Utility use, rate, sun hours, system size, roof age | NREL, EIA, IRS |
| HVAC | Equipment and tonnage | System type, size, efficiency, ductwork, region | DOE, ENERGY STAR, BLS |
| Windows | Per opening | Count, style, frame, glazing, install method, stories | DOE, NFRC, BLS PPI |
| Water heater | Unit and connections | Tank/tankless, capacity, fuel, venting, access | DOE, ENERGY STAR, BLS |
| Siding | Exterior wall area | Material, stories, tear-off, trim, sheathing repair | BLS PPI, Census housing, NAIC |
| Gutters | Linear feet | Material, seamless work, downspouts, guards, access | BLS construction/PPI, NAIC |
| Flooring | Floor area | Material, removal, leveling, subfloor, transitions | BLS labor/PPI, NAIC |
| Fence | Linear feet | Material, height, gates, ground, removal, permit | Published fence cost guides, III coverage definitions |
| Deck | Deck area | Decking material, height, railing, stairs, demolition, permit | Published deck cost guides, AWC DCA 6 |
| Claim gap | Replacement cost and age | Expected life, depreciation, deductible, ACV/RCV path | NAIC and state insurance regulators |
| Electrical panel | Panel and service size | 100A to 200A or 400A, meter base, mast, disconnect, surge, grounding | NEC, utility service rules, BLS |
| Foundation | Linear feet of wall and piers | Interior or exterior drain, sump, braces, piers, engineering | Published foundation repair guides, IRC |
| Driveway | Slab area | Concrete or asphalt, tear-out, base depth, rebar, apron | Published paving guides, ACI |
| Concrete leveling | Area lifted | Mudjacking or foam, slab type, cracks, joints, drainage | Published leveling guides, InterNACHI |
| EV charger | Circuit run in feet | Charger or outlet, amps, route, trench, panel capacity | DOE AFDC, NEC, published install guides |
| Sewer line | Linear feet of lateral | Camera, spot repair, trench or trenchless, surface cuts, city tie-in | Published sewer guides, local utility rules |
| Garage door | Per door | Size, insulation, springs, opener, safety eyes | UL 325, published install guides |
| Septic system | Tank and drain field | Tank size, trenches, pump chamber, mound or ATU, perc test | EPA septic guidance, state health codes |
| Attic insulation | Attic floor area | Material and R-value, air sealing, baffles, removal, ventilation | DOE, ENERGY STAR R-value map |
| Retaining wall | Face square feet | Height, material, drainage, geogrid, demolition | NCMA guidance, published wall guides |
| Sump pump | Per pump and basin | Pump type, backup, new basin, discharge, outlet | Published plumbing guides, IRC |
| Mold remediation | Affected area | Containment, removal, HEPA cleaning, clearance, rebuild, HVAC | EPA mold guidance, IICRC S520 |
| Whole-house repipe | Bathrooms and fixtures | PEX or copper, stories, wall patching, permits | Published repipe guides, IRC |
| Tree and tarp | Per job | Tree size, crane, tarp area, board-up, haul-away, debris limit | III coverage definitions, published tree guides |
| Service line | Linear feet of line | Trench or bore, depth, entry point, endorsement limit | Utility responsibility rules, insurer endorsements |
| Egress window | Per opening | Wall cut, window, well, ladder, drainage, permit | IRC R310, published install guides |
| Stucco remediation | Wall area | Tear-off, sheathing, barrier, drainage, re-clad | ASTM C926 and C1063, published remediation guides |
| Popcorn ceiling | Ceiling area | Lab test, protection, scraping or abatement, finish | EPA asbestos guidance, state rules |
| Crawl space | Crawl space area | Liner, wall coverage, rim foam, dehumidifier, drainage | DOE building science, published guides |
| Well pump and tank | Per pump and tank | Well depth, pump type, tank size, controls | EPA private well guidance, published guides |
| French drain | Linear feet | Trench depth, pipe, stone, basins, outlet | Published drainage guides |
| Kitchen remodel | Cabinet run and counter area | Scope, cabinet grade, countertop, sink, water damage | Published remodel cost studies |
| Toilet | Per toilet | Grade, count, flange, supply line, subfloor | Published plumbing guides, WaterSense |
| Water storage tank | Tank volume | Tank type, size, placement, booster pump, excavation | Published tank guides, EPA |
| Water filter and softener | Per system | System type, house size, UV, loop, water test | EPA, NSF/ANSI standards |
| Front door | Per opening | Material, sidelights, double door, sill pan, hardware | Published door guides, NFRC |
Companion tools sit alongside the trade calculators. They use the same rule of showing their arithmetic, but each answers a different question.
| Tool | Method | Main evidence | |
|---|---|---|---|
| Home rebuild cost | Base rate per sq ft by quality, adjusted for stories, foundation, walls, roof and region; rooms, garage, demolition and fees added; compared with Coverage A, the 80% rule, ordinance or law and loss of use | NAIC insurance definitions, BLS PPI | |
| Roof area | Footprint × √(1 + (rise/12)²), plus waste; squares converted to bundles, underlayment and trim | Geometry; ReplaceCost roof rates | |
| Roof tax | Repair or improvement by use; straight-line, mid-month depreciation over 27.5 years (rental) or 39 years (home office share) | IRS Publications 523, 527 and 587 | |
| Roof grants | Published program rules screened against answers; 2026 HHS poverty guidelines used only as a rough income screen | USDA, HUD, DOE, FEMA, SBA, HHS | |
| Should I file a claim? | Payout = damage less any ACV depreciation, less the deductible (flat or % of Coverage A); compared with premium × expected surcharge × years, weighted for prior claims | Published premium-after-claim research, NAIC | |
| Water damage | Drying rate per sq ft by IICRC category with minimums and a delay factor; flood-cut wall area from estimated room perimeter; flooring at the flooring calculator’s rates; mold allowance | Published restoration cost guides, IICRC categories, EPA | |
| Repair or replace | $5,000 rule (HVAC), 50% rule, share of expected life and recent repairs; cost per year of repairing against the new price over a full life | Trade rules of thumb, InterNACHI life expectancy, DOE | |
| AC size | Room: ENERGY STAR chart and its adjustments. Whole home: climate load per sq ft with insulation, sun, ceiling and occupant factors; 12,000 BTU per ton | ENERGY STAR, DOE, ACCA Manual J named as the professional method | |
| Roof repair | Quantity times a small-job band (patch, boot, valley or tarp), times 1.18 on two stories | ReplaceCost planning bands for asphalt repairs, kept separate from a full reroof | |
| Soffit and fascia | Linear feet of eave times material, times 1.22 on two stories, plus gutter rehang | Published per-foot eave ranges; gutter trough priced on the gutter tool | |
| Skylight | Count times flashing, replacement or new-opening band; deck-mount higher than curb | Installed residential skylight ranges, not a store box price | |
| Roof extension | New floor or roof area times a shell rate, plus tie-in by the age of the existing roof | Published dormer and small-addition ranges; bathroom excluded | |
| Overlay or tear-off | Footprint times pitch factor, in squares; overlay only if one layer and a sound deck | Architectural asphalt per-square bands; deck sheets at 3 per square | |
| House raising | Footprint times lift rate times 1.45 for two stories, plus the new foundation | Residential lifting and foundation bands; rooms underneath excluded | |
| Chimney | Fixed band for crown, flashing or tuckpoint; rebuild is height above the roof times a per-foot rate | Residential masonry ranges; height is not from the firebox | |
| Wiring and outlets | Per device, or floor area for a full rewire | New boxes, dedicated circuits, panel space | NEC device rules; published electrician ranges |
| Lighting | Per fixture | Existing box versus a new switch leg, fan bracing, IC cans | Published installed-fixture ranges |
| Private road | Length times width | Asphalt, gravel or concrete, and the base under it | Residential paving ranges |
| Painting | Paintable surface | Interior or exterior, coats, prep | Published paint labor ranges |
| Drywall | Square feet, with a patch minimum | Hang-and-finish versus a spot repair, texture | Published drywall ranges |
| Bathroom | Scope band by size | Whether the drain and valve stay put | Published remodel bands |
| Water service line | Trench length | Pipe material, street or driveway restoration | Published service-line ranges |
| Standby generator | Kilowatts | Transfer switch, pad, fuel line | Published installed standby ranges |
| Fire damage | Severity tier sets the wet, charred and structural share of the affected area; mitigation lines priced per sq ft and not depreciated; rebuild lines depreciated over 30 years; Coverage A check | Published restoration cost guides, USFA, NAIC | |
| Contents claim | Each category depreciated straight-line on its own life with a 20% floor; first check = ACV less deductible within Coverage C; receipts release the rest on RCV policies | United Policyholders, state insurance departments | |
| Loss of use | Hotel nights, rent above housing that stops, and the monthly increase in living costs, checked month by month against the Coverage D dollar and time limits | Policy forms, United Policyholders | |
| Recoverable depreciation | Check #1 = RCV less depreciation less deductible; total paid = lower of RCV and actual cost, less deductible; deposit bridge and deadline from the date of loss | Standard RCV settlement wording, state rules | |
| Roof supplement checker | Edge lengths estimated from squares and pitch; missing lines priced at 2026 insurance repair unit ranges; 20% O&P shown only with three or more trades | IRC Chapter 9, insurance repair pricing | |
| Code upgrade | Added cost of code-required items over a like-for-like repair, compared with the Ordinance or Law share of Coverage A | IIABA, ISO homeowners form, IRC | |
| Hail deductible | Percentage of Coverage A converted to dollars and taken from the claim; compared with a flat deductible | State insurance departments, policy forms | |
| Matching laws | Damaged area against the area needed for a reasonably uniform match, by state rule and evidence of discontinued products | State matching regulations, NAIC model rule | |
| Depreciation | Straight-line age over expected life with a floor; ACV and recoverable depreciation shown | NAIC, InterNACHI life expectancy |
Regional choices apply a broad labor-and-market adjustment to labor-bearing lines; they do not claim ZIP-code precision. Material lines are adjusted only when the model has a reason to do so. Complexity factors are attached to the work they affect—for example, stories affect access-heavy installation, while glazing affects the window unit itself.
A user should still obtain at least three written local quotes. Comparing scope is more useful than comparing only the final total: product model, removal, permit, disposal, flashing, trim, deck or subfloor repair, warranties and exclusions should all be written down.
The insurance layer is an educational comparison. It separates replacement cost value (RCV), actual cash value (ACV), estimated depreciation, the deductible and—where the policy permits it—potentially recoverable depreciation. The calculator uses the age and expected service life supplied or selected by the visitor.
Carrier schedules, endorsements, exclusions, special roof settlements, percentage wind/hail deductibles, matching law and claim facts vary. Only the written policy and the insurer’s claim decision determine payment. A state insurance department or licensed professional can address a specific dispute.

National labor context and price movement; not a local retail quote.
BLS construction occupationsBLS Producer Price IndexEquipment characteristics, energy use, system benchmarks and electricity prices.
U.S. Department of EnergyEIA electricity dataNREL solar analysisFrame, glazing and certified energy-performance terminology.
DOE window technologyNFRC ratingsConsumer definitions and the path to the appropriate state regulator.
NAIC ACV vs RCVState insurance departmentsHigh-impact legal, tax and incentive statements are checked when the governing source changes. Calculator rates and comparison ranges are reviewed on a scheduled basis and when credible feedback shows a material mismatch. Each calculator displays its review month; this methodology page carries a version and exact review date.
Material corrections should update the affected page, its visible explanation and its structured data together. If you have a current written quote or find a source that conflicts with a statement, send it through the corrections channel. Personal information can be removed before sending.
A range is only honest if its edges are stated. Every calculator here prices a normal job under normal conditions. The following sit outside the model, and any one of them can move a real invoice past the top of the range:
The exclusions differ by tool. A gutters estimate has no decking risk; a solar estimate has interconnection and utility variables a roof estimate does not. Read the assumptions shown next to the result you are actually using.
This is the roof geometry the calculators share, so a reader can see that “methodology” is arithmetic. Footprint 1,800 sq ft. Pitch 6:12. Waste 15%. National labor index 1.00. The same steps run on a deck or a driveway; only the rate table changes.
| Multiplier √(1 + (6/12)²) | 1.118 |
| Roof surface | 2,012 sq ft |
| Squares after waste | 23.1 |
| National installed range from those squares | $12,119 – $19,342 |
| South index 0.87 on the same house | $10,543 – $16,828 |
| Depreciation cap | 80% of the midpoint |
| Low and high stay a range | The midpoint is not a quote |
Published price guides are the check, not the input. If a guide and the model disagree, the page says so. City names are not a hidden rate table: Houston uses the South index plus whatever hail deductible the policy has; Boston uses the Northeast index. Climate details that are not labor — ice barrier, wind rating, incoming water temperature — stay in the article, not inside the multiplier.
Each row is a planning range. It is not a bid. The regional index is the same one the rest of the site uses. No ZIP-code price was invented.
| Tool | Included | Left out | Reviewed |
|---|---|---|---|
| Furnace | Cabinet by fuel and AFUE, vent, gas or circuit, condensate, optional coil, permit. | Manual J sizing, oil heat, a matched air conditioner. | 20 October 2026 |
| Ductwork | 0.12 or 0.14 ft per sq ft, or feet you type; material rate; slab package. | Asbestos abatement, Manual D design. | 20 October 2026 |
| Mini-split | First zone plus added zones, line sets, circuit, mount, permit. | Square-foot sizing, energy-credit dollars, a full panel. | 20 October 2026 |
| Patio door | Unit and labor separate, by width, panels, and material. | Impact glass, an insurance discount, a hinged front door. | 20 October 2026 |
| Basement finish | Dry-basement shell, insulation, barrier, ceiling, floor, optional bath and bar. | Waterproofing, egress dollars, a claim for new finish. | 20 October 2026 |
| Home addition | Per-foot band by type and finish, HVAC, one roof tie-in, permit. | Whole-house rebuild rate, drawings, a legal ADU, a claim. | 20 October 2026 |
| Slab leak | Detection, one repair path, concrete or drywall, finish rooms. | The meter-to-house line, a repipe priced as one spot, a promised claim check. | 20 October 2026 |
| Boiler | Boiler by fuel and type, near-boiler piping, vent or liner, optional indirect tank. | Furnace prices, oil-tank removal. | 20 October 2026 |
| Radon | System by foundation, second suction point, outlet, retest. | A price that changes with pCi/L, medical advice, a claim. | 20 October 2026 |
| Oil tank | Clean pull by location and size, samples, backfill. Contamination is a wide warning range. | An insurance promise, a named state grant, a tight price for dirty soil. | 20 October 2026 |
| Impact windows | Per-opening installed band by product and size, times the count. | A premium discount in dollars or percent. | 20 October 2026 |
| Wildfire hardening | Only the measures you turn on. Eave and wall length where they apply. | A repriced roof, an IBHS percent, a promise of renewal. | 20 October 2026 |
Same rules as the rows above: national planning ranges, widened where public US guides disagreed, then multiplied by the same regional index.
| Tool | Included | Left out | Reviewed |
|---|---|---|---|
| Asbestos removal | Material rate by amount, containment, sealed disposal, optional lab inspection and air clearance test. Encapsulation for tile and siding only. | Who may legally do the work, health advice, the new floor or insulation. | 21 October 2026 |
| Lead paint | Encapsulation, enclosure or stripping by area, openings, inspection or risk assessment, cleanup, disposal, clearance rounds. | Medical advice, a grant promise, new windows or siding. | 21 October 2026 |
| Termite damage | Treatment, then each part: sistered joists, sill plate with shoring, studs, subfloor, trim, optional engineer letter. | A treatment product pick, coverage beyond the hidden-insect collapse exception. | 21 October 2026 |
| Cast iron drains | Under-slab trench, tunnel or lining by the foot, basement run, stack by story, finish rooms, camera, permit. | The sewer lateral to the street, supply pipe, a promise that lining fits. | 21 October 2026 |
| Ice dam | Steaming hours by dam size, optional roof snow, heat cable by eave length, an inside patch band. | Attic air sealing and insulation dollars, DIY roof advice, a coverage decision. | 21 October 2026 |
The seventeen calculators added on 20 and 21 October 2026 went through a second review on 21 October 2026. The aim was simple: every number a reader sees on those pages should come from the same arithmetic as the calculator, and every part of the job should be visible on its own line instead of being folded into one big total.
| Tool | What sets the price | Stop or warning rule | Primary references |
|---|---|---|---|
| Furnace | Fuel and AFUE tier set the installed band; venting, gas or circuit, condensate, coil and access are added lines. | Federal 25C credit is not applied (ended for 2026 installs). | DOE Energy Saver, ENERGY STAR, ACCA Manual J |
| Boiler | Fuel and standard vs condensing set the band; piping, vent or condensate, liner and indirect tank are lines. | Oil tank removal is never hidden inside the boiler; it points to its own tool. | DOE Energy Saver, ENERGY STAR, AHRI directory |
| Ductwork | Feet (typed, or 0.12/0.14 ft per sq ft) × material rate, +8% for attic or crawl; slab ducts are a package. | Suspected asbestos or mold stops the price. | ENERGY STAR duct sealing, DOE, ACCA Manual D |
| Mini-split | First zone carries the outdoor unit; each added zone, line set, condensate and sleeve scale by head. | Panel upgrades are excluded, not guessed. | DOE Energy Saver, ENERGY STAR, NEEP cold-climate list |
| Patio door | Unit price by width, panels and material; labor by insert vs full frame and width. | Impact glass stops and links to the impact tool. | ENERGY STAR, NFRC |
| Basement finish | Per-sq-ft wall, insulation, barrier, ceiling and floor rates; bath, bar and permit are fixed lines. | A wet basement stops the price. | DOE Energy Saver, ICC IRC, EPA radon and mold guidance |
| Home addition | Per-sq-ft band by type and finish level; HVAC, roof tie-in, bath, kitchenette and permit are lines. | Design, engineering and impact fees are named as excluded. | ICC IRC, ACCA Manual J |
| Slab leak | Detection plus one repair path; two leaks scale to 1.7×; concrete, drywall, flooring and dry-out are lines. | Three leaks or polybutylene stop and point to a repipe. | EPA WaterSense, ICC, NAIC |
| Radon | Foundation type sets the system band; second point, closet route, sealing, outlet, manometer and retest are lines. | The pCi/L reading never changes the price. | EPA radon guides, CDC, AARST standards |
| Oil tank | Location and size set the clean-pull band; pumping, tight access, samples, backfill and patch are lines. | Known contamination switches to an $8,000–$80,000 warning range. | EPA UST program, NORA |
| Impact windows | Per-opening rate by product × size × story height; haul-away, rot and permit are lines. | No insurance discount or grant is promised. | Florida Building Commission, My Safe Florida Home, FEMA, IBHS |
| Wildfire hardening | Only measures switched on; eave and wall length drive per-foot lines. Defaults to vents, gutters and the 0–5 ft zone. | A Class A roof is never repriced here. | IBHS Wildfire Prepared Home, NFPA Firewise, CAL FIRE, USFA |
| Asbestos removal | Material rate × amount; containment, sealed disposal, lab samples and air clearance are lines. | Encapsulation is only offered for tile and siding. | EPA asbestos guidance, OSHA |
| Lead paint | Method rate × painted area; openings, testing, containment, disposal, clearance rounds and repaint are lines. | No grant or medical advice is given. | EPA RRP program, HUD lead hazard control, CDC |
| Termite damage | Treatment, then each damaged piece counted: joists, sill feet with shoring, studs, subfloor, trim, engineer letter. | Insurance is treated as almost never paying. | EPA, National Pest Management Association |
| Cast iron drains | Per-foot rates by location and method (trench, tunnel, lining); stack per story; finishes per room. | The sewer line to the street is excluded. | ICC plumbing chapters, NASSCO |
| Ice dam | Steaming hours by dam size × hourly rate; snow removal, heat cable per foot and inside patch are lines. | Attic air sealing is named as the real fix, priced elsewhere. | Building Science Corporation BSD-135, DOE air sealing, ENERGY STAR |
None of these pages gives a bid, a coverage decision, medical advice or a grant promise. A written quote from a contractor who has seen the property is still the number to act on; these pages help you read that quote line by line.
Six of these are claim-math tools (flood gap, water backup, coinsurance, hurricane deductible, Coverage B and public adjuster fee). They apply policy arithmetic to the dollar figures you enter and use no regional factor. The other twenty-four price a job line by line in the same way as every other estimator on the site, using national 2026 bands and the shared regional index.
| Tool | What sets the price | Stop or warning rule | Primary references |
|---|---|---|---|
| Flood gap | Which policy answers rising water, a burst pipe or a backup, and what stays unpaid. | The adjuster decides the cause; seepage and surface water are not homeowners losses. | FEMA FloodSmart, eCFR, NAIC, Mississippi Insurance Department |
| Water backup | How one backup sublimit splits across drying, rebuild and contents, and the shortfall. | Overland water through a window well is sent to the flood gap calculator. | MoneyGeek, Mississippi Insurance Department, FEMA FloodSmart, NAIC |
| Coinsurance (80%) | What an 80% or 90% clause takes off a partial claim when Coverage A is too low. | An extended or guaranteed replacement endorsement can change the penalty; read it first. | Property Insurance Coverage Law, NAIC, Insurance Information Institute |
| Hurricane deductible | Turns a 1% to 5% hurricane or wind deductible into dollars and checks a storm loss against it. | Hail outside a named storm is sent to the hail deductible calculator. | Insurance Information Institute, NAIC, NAIC |
| Other structures (Cov B) | Coverage B ceiling, depreciation and the out-of-pocket gap for detached buildings and fences. | Business or rental use sets the Coverage B lines to $0. | MoneyGeek, NAIC, Mississippi Insurance Department |
| Public adjuster fee | Net cash for repairs if you accept the offer, hire a public adjuster or invoke appraisal. | A full denial is not an appraisal question; no national fee cap is assumed. | Conventus Law, Claims Journal, NAIC |
| Load-bearing wall | Engineer, shoring, LVL or steel beam, posts, footing, hidden utilities and patch. | The engineer sizes the beam; an unknown wall prices only the site check. | Bob Vila, International Code Council |
| Tub to shower | Prefab, tiled or curbless base, waterproofing, valve, walls, glass and drain move. | Moving the drain opens the floor or ceiling below and is its own line. | Angi, This Old House, International Code Council |
| Subfloor | Plywood or OSB by the square foot, joist sistering, blocking, haul-off and crawl access. | Three or more rotten joists or a soft girder calls for a carpenter or engineer. | Angi, Fixr, International Code Council |
| Tree removal | Priced by trunk diameter and drop zone, with crane, stump grinding and haul-away. | A tree on a house after a storm is the tree and tarp calculator; wires go to the utility. | Bob Vila, This Old House, Maryland Insurance Administration, International Society of Arboriculture |
| Concrete patio | Broom concrete, exposed aggregate or pavers per square foot, with base, old slab and steps. | Same installed concrete bands as the driveway; settled slabs go to concrete leveling. | Angi, Bob Vila |
| Detached garage | One- or two-car shell: slab, framing, roof, siding, service door and insulation. | The overhead door and any apartment above are priced elsewhere. | Angi, HomeServe, International Code Council |
| Whole-house rewire | Rewire by living area and wall type, or pigtail aluminum circuits, with patching and permit. | A panel upgrade is a separate page; knob-and-tube under insulation is flagged. | Bob Vila, U.S. CPSC, NFPA, Electrical Safety Foundation International |
| Gas line | Black iron, CSST or buried PE per foot, appliance shutoffs, bonding, test and permit. | The installer sizes the pipe; meter or regulator upgrades are left to the utility. | HomeAdvisor, Fixr, International Code Council |
| Ejector pump | Ejector or grinder pump swap, valves, alarm, or a new sealed basin under the slab. | Only swaps and new basins; the bathroom itself is priced elsewhere. | Angi, International Code Council, MoneyGeek |
| Interior doors | Slab or prehung, hollow or solid core, closet, French and pocket doors, finish and hardware. | Interior doors only; exterior and patio doors have their own pages. | Fixr, Homewyse |
| Sunroom | Screen room, three-season or four-season room on new footings or a reinforced deck. | Screen and sunrooms are not priced at the home addition rate. | Fixr, Bankrate, International Code Council |
| Covered porch | Structural columns, floor framing and decking, rails, footings and the porch roof. | A wrap over a rotted post is not counted as a structural repair. | HomeAdvisor, International Code Council |
| Patio cover | Aluminum panels, framed shingle roof, pergola or steel carport, with footings and ledger. | Local code decides snow and wind loads; freestanding covers are usually Coverage B. | Fixr, International Code Council |
| Wheelchair ramp | Ramp length from the rise at 1:12 or 1:16, landings, rails, footings and threshold. | Landings at the door, at turns and every 30 ft of run are always counted. | Bob Vila, Fixr, International Code Council, U.S. Access Board, IRS |
| Well drilling | Rig setup, drilling per foot, casing, grout seal, cap, yield test and permit. | No gallons-per-minute promise; pump and tank are priced after depth and yield. | Bob Vila, U.S. EPA, National Ground Water Association |
| Demolition | Selective tear-out, dumpsters, utility disconnects and foundation removal, with a hazard stop. | Pre-1980 homes stop for asbestos and lead testing before any tear-out is priced. | Fixr, HomeAdvisor, U.S. EPA, U.S. EPA |
| Wind mitigation | Deck re-nailing, roof-to-wall straps, sealed roof deck and the inspection form. | No discount percentage is assumed; the carrier credit stays blank until quoted. | Citizens Property Insurance (Florida), IBHS, Insurance Information Institute |
| Hurricane shutters | Storm panels, fabric, accordion, colonial or roll-down per opening, with permit. | Opening protection credit needs every glazed opening covered. | Fixr, HomeServe, Florida Building Commission, IBHS |
| Pier and beam | Re-shim or rebuild piers, sister or replace girders and sill plates, with engineer. | Moisture and drainage are fixed first, or the repair is redone. | Angi, International Code Council |
| Lightning & surge | Electrician testing, breakers and surge device, HVAC boards, well pump and appliances. | Direct strike and grid surge are treated differently by many policies. | MoneyGeek, NFPA, Electrical Safety Foundation International |
| Shower pan leak | Flood test, tear-out, new liner or membrane, lower wall tile, curb and subfloor rot. | Ceiling and mold work below the shower are priced on their own pages. | Angi, Tile Council of North America, International Code Council |
| Stair railing | Wood, iron, cable or glass per linear foot, newel posts, fittings, tear-out and finish. | Exterior deck, porch and ramp railings are priced elsewhere. | HomeAdvisor, Bob Vila, International Code Council |
| Pool cage | Panel repair, full rescreen, mesh upgrade, doors, fasteners or a full cage rebuild. | Pool shell, equipment and deck levelling are excluded. | HomeAdvisor, Florida Building Commission |
| Ridge vent | Shingle-over or metal ridge vent per foot, closing old vents, baffles and access. | A ridge vent needs matching soffit intake, priced separately. | Angi, International Code Council, ENERGY STAR |
Every one of these pages was checked the same way before publishing: each calculator was run at its default inputs and with every option, the default result was matched against the worked example on the page, and code and policy citations were checked against the issuing body.
After the thirty new pages went live, every calculator on the site, all 116 of them, went through one more pass. The checks below now apply to every tool, not only the newest ones.
Range figures did not change in this review. When a rate is updated, the date at the top of that page changes with it.
No, and a single exact number would be less honest than a range. Final cost depends on inspection, site access, scope, product choice and conditions nobody can see before work starts. The range is the planning tool; a written quote from a contractor who has seen the property is the number you act on.
Category rates are cross-checked against current published pricing from several national cost publishers, then adjusted for measurable factors the publishers average away: pitch, waste, tear-off layers, access and regional labor. Public sources are used for labor context and for insurance and regulatory definitions. Each page lists the sources it relied on.
Usually scope rather than price. Check whether the quote includes tear-off, disposal, underlayment, flashing, ventilation, drip edge, a decking allowance, the permit and cleanup, because a quote missing three of those will look cheaper without being cheaper. After that, local labor conditions and product choice explain most of what is left.
Not to that resolution. It applies a broad regional labor index, which is a planning adjustment rather than local pricing. A metro with high storm demand can sit well above its own regional index for months after a major event. Where a page has genuinely local information, such as city permit fees, it says so and cites it.
Yes. Installed cost is what the tools estimate, because material-only figures are of little use to a homeowner comparing quotes. The itemized result separates the material and install line from tear-off, decking and permit so you can see where the money sits.
It does, as a separate step rather than folded into the cost. Depreciation is modeled straight-line against the material's expected life and floored at a residual value, then shown alongside the replacement range so you can see the replacement figure and the depreciated figure as two different things. Your carrier uses its own schedule.
No. It has never seen your policy. It applies the deductible and settlement type you enter, which is arithmetic, not a coverage determination. Whether a loss is covered depends on the cause, the policy wording, exclusions, roof condition and the approved scope, and only your insurer decides that.
Use it to prepare, not to argue. It helps you see whether a carrier estimate looks short on scope and which questions to ask. It is not an appraisal and carries no weight in a settlement. The document that does that work is a written, itemized estimate from a contractor who has inspected the property.
No inputs leave your browser. Saving an estimate writes it to your own device's local storage so the form is still filled in when you return, and the Clear button removes it. Nothing is transmitted, and no email address is required to see a result. The privacy page sets out what is and is not stored.
Send the page address, the exact inputs you used, the result you got and the figure you are comparing against, ideally a written quote with personal details removed. That is enough to trace the assumption. Reports that do not lead to a change get a reason rather than silence. Use the contact page.